Project Data:Period of work: 24 months ( July 1999 – July 2001 )
Description of work : Fine finishing works and façade finishing works
Architect: Cannon Design
Client: Sabancı Vakfi
Main Contractor: Koray Yapı Endüstri ve Tic. A.Ş.
Scope of our works: Material supply and workmanship of finishing works and Alsecco façade cladding system
· Façade cladding; 29,500 m2
· Brickwork; 9,241 m2
· Cement plastering; 45,532 m2
· Gypsium plastering; 111,907 m2
· Screed; 33,891 m2
· Road borders ; 1,083 m
· Door and window lintels ; 10,744 m